First confirm the electricity supply authority
A property within the City of Cape Town electricity supply area follows City application and metering arrangements; an Eskom-supplied property follows a different process. The owner’s electricity account and point of connection establish who must approve export. Not every existing solar system was designed to feed electricity into the network, and an approved generation installation does not automatically mean the property is approved for export. We begin with the supply authority, the current authorisation documents and the inverter model.